Compare and contrast the Critical Path and Critical Chain methods intermsof their advantages: Project Management Assignment, UM, Malaysia
University | University of Malaysia (UM) |
Subject | Project Management: Survival and Success |
Compare and contrast the Critical Path and Critical Chain methods intermsof
their advantages and deficiencies to conclude on what would be the most
suitable approach to planning and delivering a Glastonbury music festival
The Critical Path and Critical Chain approaches are both utilized in project
management to effectively plan and execute projects. Let’s examine and differentiatethese methods within the context of organizing and delivering a Glastonbury musicfestival : Critical Path Method (CPM)
Get Solution of this Assessment. Hire Experts to solve this assignment for you Before Deadline.
Benefit
i. CPM has the ability to reduce project duration and generate crucial paththat canas a road map for project execution, ensuring timely project completion. (Atin.S,2019)
ii. CPM can contribute to the temporal effectiveness and financial aspects of theproject in distinct ways. (Atin.S , 2019)
iii. CPM focuses on the planning, scheduling and control of these critical activities.
iv. (Anindita.H , 2021)
v. In CPM, one of its main purposes is to plan and set important and desiredresultsfor the project’s final completion.(Anindita.H , 2021)
Deficiencies
i. Not all projects are suitable for the critical path method due reduced usability. For instance, CPM requires and repeatable timelines(dummy activities becomesexcessive), making it unsuitable for creative projects like product designor research tasks.(J.Hutagaol,2013)
ii. CPM schedules do not consider resource constraints, equipment or labor
resource availability. Additionally, CPM fails to highlight resource duplication, potentially causing congestion and can lead to inefficient resource allocationespecially the addition of human resources (J.Hutagaol,2013)
Critical Chain Management
Benefit
i. 1.Resource-driven planning: CCM prioritizes resource availability and toguarantee the most allocation of resources.
ii. 2.Buffer management: It includes the concept of project buffers to protect against uncertainties and delays, allowing for better project control.It will also indirectlyreduce the pressure on the workforce.(Rahayu.S,2022).
Stuck in Completing this Assignment and feeling stressed ? Take our Private Writing Services.
Get Help By Expert
Elevate your academic achievements with our exceptional services in Malaysia assignment helper and personalized homework writing help for your Project Management assignments. We understand the challenges students face, and our dedicated experts are here to provide tailored assistance. Now, Malaysia students can easily enhance their project management skills by paying our seasoned professionals for expert guidance.
Recent Solved Questions
- LAW416: Business Law Assignment, UiTM, Malaysia Lena a housewife, visits Tenggara Bhd, a company that sells various kinds of electrical goods for household purposes
- Object Oriented Development with Java Assignment, APU, Malaysia Design and implement a Hostel Management System and the target users are admin and student
- DBAF2003: Principles of Accounting Assignment, UoC, Malaysia On 1 January 2011, Yen had two vehicles for use in his business. Vehicle X was bought several years earlier for £7.500
- Discuss on how character education in the future 2027 school curriculum in Malaysia: Foundations Of Educations Assignment, UNM, Malaysia
- Management Accounting Techniques Assignment, UTIM, Malaysia Capital Investment becomes a crucial investment decision in an uncertain economic environment needs to be made
- Energy Economics Report, SU, Malaysia With climate change, water scarcity will likely be amplified due to drought and wildfire coupled with increasing demand
- CHE433 Thermodynamics Assignment, UiTM, Malaysia Velocity is an intensive property of a system and One kilogram of water at a temperature of 225°C and 500 kPa has a volume of 0.078405 m3
- MLL207e: Comparative Study of Bahasa Melayu and Bahasa Indonesia Assignment, SUSS, Malaysia Huraikan secara kritis sejarah perkembangan Bahasa Indonesia dan Bahasa Melayu dalam kurun ke-20
- English Home Work, UPM, Malaysia There have been large extinctions throughout Earth’s history. The most famous of these caused the end of the dinosaurs
- BBMP1103: A manufacturer sells a product at a price of RM150 per unit. The labour and material costs are RM20: Mathematics For Management Assignment, OUM, Malaysia